SR 3 - Belfair Bypass - New Alignment

Quarterly Project Report Update for Quarter Ending June 2006

Project Title & Location
SR 3 - Belfair Bypass - New Alignment

Project Description
The proposed Belfair Bypass solves both the immediate and long-range transportation safety and mobility needs of the SR 3 corridor in northeast Mason County.

Contractor/Consultant
Skillings-Connolly, Inc. Consulting Engineers

Recent Progress
Skillings-Connolly, Inc., has been selected as the consultant to complete the Environmental Assessment.

Design Construction Impacts
Will be evaluated and determined as a result of environmental studies and preliminary design.

Environmental Impacts / Compliance
Will be evaluated and determined as a result of environmental studies and preliminary design.

Impacts to Traffic
The proposed project will be a new corridor; there will be very minimal impacts to traffic.

Project Milestones Scheduled Attained Milestone Outlook
Consultant chosen to complete Environmental Assessment March 15, 2006 This was formerly a county lead project and the scope is not completely defined.  Future milestones and complete phase costs are still being developed.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 10.0 66.7 %
Right-of-Way 5.0 33.3 %
Construction 0.0 0.0%
Funded Project Costs 15.0 100.0%

Nickel funds included in above costs

0.0 0.0%

2005 Transportation Partnership Account

15.0 100.0%

  For more information, go to www.wsdot.wa.gov/projects

Amity Trowbridge, Project Engineer, (360) 357-2682