SR 290 - Mission Ave to Sullivan Rd - Paving

Status

August 2017

  • Weekly Construction Update
  • Under construction.
  • Awarded to CPM/Inland Asphalt Company of Spokane with a construction bid of $3,464,647.

SR 290, Trent Avenue will be resurfaced from the Mission Ave. "Y" to Sullivan road. In addition, the bridge deck on the Spokane River Bridges near Pines road will be repaired and the eastbound SR 290/UPRR bridge deck will be repaired.

Why is WSDOT resurfacing this highway?
High traffic volumes with normal wear and tear has deteriorated the pavement surface and three bridge decks.

The End Result
A smoother roadway and protection for the underlying highway structure.

Project Benefits
A better experience for drivers with a reduced need for repairs and patching.

What is the project timeline?
The project will be designed, advertised for bids and constructed during 2017.

Financial Information

Financial Data for PIN 629000X, 629000Y
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $4,735
CWA $0
Total $4,735

Project signage will reflect the cost of construction engineering, project bid award and sales tax.

How can I get more information?
Contact:
Larry Larson, Project Engineer
WSDOT Eastern Region
2714 N. Mayfair
Spokane, WA  99207
509-324-6000
larsolr@wsdot.wa.gov

back to top