SR 285 - W End George Sellar Bridge - Intersection Improvement

Quarterly Project Report Update for Quarter Ending September 2008

Project Title & Location
SR 285/W End of George Sellar Bridge-Intersection Improvement-Wenatchee

Project Description
This project will remove the left turn movement from SR 285 onto southbound Mission Street, which will increase the capacity of the intersection. It will also provide for an additional westbound lane approaching the intersection. This lane will direct traffic to local streets including southbound Wenatchee Avenue. Multiple improvements to the local system will also be constructed.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
Design work continues.  A VE study was held the week of July 28th for the staging and hydraulics aspects of the project.  A noise analysis study is underway to determine the impacts to local businesses and residents.

Design Construction Impacts
Numerous parcels will be affected by this project.  The extent of the impact will be determined as the design moves ahead.  The right of way process will begin in the winter of 2008/2009.  The community and local agencies will continue to be an integral part of our development process.

Environmental Impacts / Compliance
Under NEPA guidelines, the project has been categorized as a Documented CE (Categorical Exclusion).  The Draft Environmental Classification Summary has been completed.

Impacts to Traffic
Traffic will be impacted on both SR 285 and the local street system.  Lane closures can be anticipated.  Traffic control plans will be developed as the design progresses.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised October 18, 2011 No issues at this time.
Contract Awarded December 1, 2011 No issues at this time.
Groundbreaking May 15, 2012 No issues at this time.
Open to Traffic November 1, 2012 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.8 m 11%
Right-of-Way $4.24 m 26%
Construction $10.14 m 63%
Funded Project Costs $16.18 m 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

$12.70m 78%

  For more information, go to www.wsdot.wa.gov/projects

Eric Pierson, WSDOT Project Engineer @ (509) 667-2870 or E-Mail: Piersoe@wsdot.wa.gov