SR 285 - George Sellar Bridge - Additional EB Lane

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location
SR 285/George Sellar Bridge-Additional EB Lane

Project Description
This project adds an additional eastbound lane to the George Sellar Bridge by removing the existing sidewalks. Pedestrian movements will be addressed by providing alternative access across the bridge.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
The bridge office is finalizing their model of the bridge modifications and developing preliminary bridge plans.  The region design team is coordinating geotechnical drilling, working on traffic staging plans, and working with the railroad.

Design Construction Impacts
We are investigating the staging requirements between this project and the projects at either end of the bridge.  This project will be a two season project.

Environmental Impacts / Compliance
The Sellar Bridge is on the national historic register.  A 4f style process at the State level will be required for bridge truss modifications to allow for sufficient vertical clearance.  A hydraulics permit and shorelines permit will also be required.

Impacts to Traffic
This project will heavily impact commuter traffic.  The region is investigating the use of night shifts to minimize construction impacts to the traveling public.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised December 8, 2008 No issues at this time.
Contract Awarded January 15, 2009 No issues at this time.
Groundbreaking April 25, 2009 No issues at this time.
Open to Traffic December 1, 2010 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.77 7%
Right-of-Way $0.01 1%
Construction $10.2 92%
Funded Project Costs $10.94 100%

Nickel funds included in above costs

$0 0%

2005 Transportation Partnership Account

$10.94 100%

  For more information, go to www.wsdot.wa.gov/projects

Kevin Waligorski, WSDOT Project Engineer @ (509)667-2860 or Email:  WaligoK@wsdot.wa.gov