Project Title & Location
SR 285/George Sellar Bridge-Additional EB Lane
|
Project Description
This project adds an additional eastbound lane to the George Sellar Bridge by removing the existing sidewalks. Pedestrian movements will be addressed by providing alternative access across the bridge.
|
|
Contractor/Consultant
Project not yet advertised or awarded.
|
|
Recent Progress
The bridge office has completed preliminary plans and is continuing their design work. The geotechnical office has completed drilling test holes and the design team is coordinating with the railroad and developing traffic staging plans. Coordinating with BNSF on easement and agreement issues.
|
|
Design Construction Impacts
We are investigating the staging requirements between this project and the projects at either end of the bridge. This project will be a two season project. Significant coordination with BNSF will be required while constructing the walkway over the railroad.
|
|
Environmental Impacts / Compliance
The Sellar Bridge is on the national historic register. A 4f style process at the State level has been conducted with DAHP (SHPO) to assess needed bridge modifications. A hydraulics permit and shorelines permit will also be required.
|
Impacts to Traffic
This project will heavily impact commuter traffic. The region is planning to use night shifts to minimize construction impacts to the traveling public.
|