Project Title & Location
SR 285/George Sellar Bridge-Additional EB Lane
|
Project Description
This project adds an additional eastbound lane to the George Sellar Bridge by removing the existing sidewalks. Pedestrian movements will be addressed by providing alternative access across the bridge.
|
|
Contractor/Consultant
Project not yet advertised or awarded.
|
|
Recent Progress
The executed agreement with BNSF was received November 24th. The bridge office has completed their analysis and is finalizing the bridge plans. The plans in hand review was held December 1st and 2nd.
|
|
Design Construction Impacts
We are investigating the staging requirements between this project and the projects at either end of the bridge. This project will be a two season project. Significant coordination with BNSF will be required while constructing the walkway over the railroad.
|
|
Environmental Impacts / Compliance
The Sellar Bridge is on the national historic register. A 4f style process at the State level has been conducted with DAHP (SHPO) to assess needed bridge modifications. A hydraulics permit and shorelines permit will also be required.
|
Impacts to Traffic
This project will heavily impact commuter traffic. The region is planning to use night shifts to minimize construction impacts to the traveling public.
|