SR 28 East Wenatchee Corridor Improvements

Status

Winter 2017-18

Phases 3 & 4 of this Eastside Corridor improvement is scheduled for design in 2019 and completed construction in 2027.

This project enhances safety and mobility on SR 28 in East Wenatchee from 9th Street to Hadley Street with intersection improvements and widening the existing roadway to accommodate five lanes including median turn lanes in places.

Why is WSDOT improving mobility through this section of Sunset Highway?
Additional lanes and access controls such as concrete barricades in the median will address both collisions and traffic back ups through this heavily travelled section of highway.

The End Result
Fewer collisions and smoother traffic flow

Project Benefits
Fewer delays through a safer corridor.

What is the project timeline?

  • Design 2020 through 2024
  • Right of Way 2020 through 2024
  • Construction 2024 through 2027

Financial Information

Project signage will reflect the cost of construction engineering, project bid award and sales tax.

How can I get more information?
Contact:
David Bierschbach, P.E.
North Central Region
Assistant Region Administrator for Engineering
509-667-3030
BierscD@wsdot.wa.gov

back to top