Project Title & Location
SR 28 - Junction US 2/97 to 9th Street - Stage 1 - East Wenatchee

Project Description
This project will provide necessary improvements to the SR 28 and US 2/97 intersection to allow for the Eastmont Extension tie-in as well as increasing the number of lanes on each leg of the intersection and paving with portland cement concrete pavement.

Contractor/Consultant
This project will be divided into several contracts with the first contract being advertised for competitive bidding in the Fall of 2008.  Portions of this project are being developed by Douglas County.  The county is utilizing consultants.

Recent Progress
WSDOT and Douglas county are working on designing the projects.  WSDOT is finalizing the intersection and right of way plans for the intersection piece.

Design Construction Impacts
There will be impacts to adjacent property owners and utilities.  After the design and right of way plans are completed, the exact impacts will be determined.

Environmental Impacts / Compliance
All environmental documents and permits are on time.

Impacts to Traffic
Construction staging plans are under development in conjuction with possible detour plans to minimize the impact to the traveling public.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering April 24, 2006 April 24, 2006 Completed
Environmental Documentation Complete September 8, 2009 No issues at this time.
Right of Way Certification October 16, 2009 No issues at this time.
Advertisement Date November 16, 2009 No issues at this time.
Operationally Complete October 16, 2011 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $5.42 10%
Right-of-Way $6.97 13%
Construction $41.53 77%
Funded Project Costs $53.91 100%

Nickel funds included in above costs

$0.0

2005 Transportation Partnership Account

$53.91 100%