SR 28 - E. End of the George Sellar Bridge

Quarterly Project Report Update for Quarter Ending March 2006

Project Title & Location
SR 28/E. End of the George Sellar Bridge

Project Description
This project reconstructs portions of the SR285/SR28 interchange on the east end of the George Sellar Br. in East Wenatchee. The main improvement is the addition of a bypass route for southbound SR 28 traffic. This relieves congestion at the intersection of SR 28 and Grant Rd. and allows a triple left turn movement, optimizing capacity of the signal there. This is phase one of a two phase project (2nd phase unfunded), to ultimately construct a Single Point Urban Interchange at the intersection.

Contractor/Consultant
Project not yet advertised or awarded

Recent Progress

Presentations have been made to the Wenatchee Valley Transportation Council, Regional Transportation Planning Organization, East Wenatchee City Council, East Wenatchee Rotary Club, Top Foods and Fred Meyer Representatives, and other impacted property owners informing them of the preliminary layout of this project.   An open house was held on June 10, 2004, with 120 people in attendance.  A design open house/access hearing was held in May 2005.  A relocation plan for the PUD transmission line within the project limits has been developed. Geotechnical borings were completed November 10, 2004. 

Design Construction Impacts
 The innovative bypass design requires acquisition of a portion of the Fred Meyer parking lot for the new roadway.  The parking lot is built on an embankment  created by a 30+ ft high retaining wall.  The bypass design extends this retaining wall for a distance of 1900 ft paralleling the Columbia River, while maintaining a buffer of natural terrain along the shoreline.  A Chelan County PUD transmission line will be relocated for the project.  Close coordination is ongoing with the City of East Wenatchee, Douglas County, the Wenatchee Valley Transportation Council (MPO) and local businesses to keep these stakeholders informed on project development.  This project will alter traffic patterns and access to Fred Meyer and other properties.  These impacts are being resolved through the Access Hearing process.

Environmental Impacts / Compliance
 The appropriate environmental documents are determined to be a NEPA Documented Categorical Exclusion (CE) and a SEPA Determination on Non-Significance (DNS) with checklist A draft Environmental Classification Summary is complete.  Section 106 consultation is in progress, with a completed cultural resource survey and writing of Memorandum of Agreement on mitigation of proposed impacts to identified cultural sites.

Impacts to Traffic
 The majority of this project can be constructed with little disruption to traffic on SR28 or SR285.  Traffic using the Fred Meyer parking lot will have minor impacts.  When connections are made to SR28/SR285 traffic will need to be shifted onto the shoulder and/or detoured briefly.  During the construction of the added lane on Grant Road access to businesses will be temporarily impacted, and possible lane closures will be needed.  

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised October 2008 No issues at this time
Contract Awarded November 2008 No issues at this time
Groundbreaking April 2009 No issues at this time
Open to Traffic October 2009 No issues at this time
 
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.230 13.1%
Right-of-Way $2.330 24.9%
Construction $5.800 62.0%
Funded Project Costs $9.360 100%

Nickel funds included in above costs

$0.000 0%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Mike Andreini, WSDOT Design/Plans Engineer @ (509)667-3042 or Email:  andreim@wsdot.wa.gov