SR 28 - E. End of the George Sellar Bridge

Quarterly Project Report Update for Quarter Ending March 2004

Project Title & Location
SR 28/E. End of the George Sellar Bridge

Project Description
This project reconstructs portions of the SR285/SR28 interchange on the east end of the George Sellar Br. in East Wenatchee. The main improvement is the addition of a bypass route for southbound SR 28 traffic. This relieves congestion at the intersection of SR 28 and Grant Rd. and allows a triple left turn movement, optimizing capacity of the signal there. This is phase one of a two phase project (2nd phase unfunded), to ultimately construct a Single Point Urban Interchange at the intersection.

Contractor/Consultant
Project not yet advertised or awarded

Recent Progress

WSDOT completed a Value Engineering (VE) Study for this project on October 24, 2003.  The recommendation was a two phase project.  Phase 1 was a SR28 southbound bypass and a  triple left for  traffic turning left onto Grant Road.  Phase 2 was the construction of a Single Point Urban Interchange at the junction of SR28 and Grant Road.  The VE recommendations were accepted.  A Cost Risk Assessment was completed on this project in November 2003.  The Design Team is currently in the process of developing a  Public Involvement Plan and Project Delivery Plan. Presentations have been made to the Metropolitan Transportation Planning Organization, Regional Transportation Planning Organization, East Wenatchee City Council, and Fred Meyer Representatives informing them of the Preliminary layout of this project.  

Design Construction Impacts
 It is proposed to use the existing retaining wall constructed by Fred Meyer for this project.  This will involve acquiring a portion of the Fred Meyer parking lot for this alignment which will have an impact to their access and parking lot.  The Chelan PUD has a aerial power line in the vicinity of this bypass which will require some relocation.  There are also several businesses and a City of East Wenatchee drainage easement that will be impacted by this project .  Close coordination will be needed with the City of East Wenatchee, Douglas County, Fred Meyer and other businesses for this project.  A design/access hearing will be required on this project and will be scheduled for early spring 2005.

Environmental Impacts / Compliance
 Coordination with NCR Environmental staff is needed to determine what level of Environmental documentation is needed for this project.  Preliminary meetings and communications with resource agencies indicate that a Documented CE (Categorical Exclusion) will be used.  A Draft Environmental Classification Summary will be completed in the very near future.

Impacts to Traffic
 The majority of this project can be constructed with little disruption to traffic on SR28 or SR285.  Traffic using the Fred Meyer parking lot will have minor impacts.  When connections are made to SR28/SR285 traffic will need to be shifted onto the shoulder and/or detoured briefly.  During the construction of the added lane on Grant Road access to businesses will be impacted, and possible lane closures will be needed.  

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised October 2008 No issues at this time
Contract Awarded November 2008 No issues at this time
Groundbreaking April 2009 No issues at this time
Open to Traffic October 2009 No issues at this time
 
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.230 13.1%
Right-of-Way $2.330 24.9%
Construction $5.800 62.0%
Funded Project Costs $9.360 100%

Nickel funds included in above costs

$0.000 0%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Terry Berends, WSDOT Design/Plans Engineer @ (509)667-3041 or Email:  berendt@wsdot.wa.gov