WSDOT Projects

text size: T T T

SR 28 - East Wenatchee Area - Paving

Construction will begin in June
Project Map

View entire map.  This project paves 2.82 miles of SR 28 from 9th St. to the US 2/97 and SR 28 intersection, excluding the SR 28/East Wenatchee 31st to Hadley Project that was constructed in 2007. It also paves 1.52 miles of US 2/97 north of the US 2/97 and SR 28 intersection.

SR 28 looking south at approximately MP 0.28B.

View entire photo.  This section of SR 28 will be paved to provide a smoother driving surface.
Project Facts
  • This project paves almost 3 miles of SR 28 and 1-1/2 miles of US 2-97.
  • In addition to new pavement, the project includes curb and gutter, guardrail, new striping and pavement markings, centerline rumble strip and sidewalk.
  • Construction will take six weeks (30 working days).

Project Status

Spring 2008

This project was advertised for private contractor bids in April. A contract was awarded to Basin Asphalt on May 12th for $1.2 million, 20% under the engineering estimate. Construction should begin in July. 

This preservation project paves 2.82 miles of SR 28 from 9th Street to the US 2/97/SR 28 intersection, excluding the section from 31st to Hadley paved during last summer's widening project. It also paves 1.52 miles of US 2/97 north of the Odbashian Bridge intersection.

Why is WSDOT paving SR 28 and US 2/97?
This section of SR 28 and US 2/97 is due for pavement restoration due to deterioration.

The End Result
The project will prevent further deterioration to the existing roadway at the least possible "life cycle" cost.

Project Benefits

  • Extends roadway life.
  • Provides a smoother driving surface.

What is the project timeline?
Construction should begin in July and will take six weeks (30 working days) to complete.

Public Involvement
Your thoughts and ideas are important to us.  If you have questions or concerns about this project, please contact us.  Contact information is listed below.

Environmental Protection
All applicable environmental laws and guidelines are being followed.  No environmental permits are anticipated to be required for this project.
Please visit the WSDOT Environmental Services Web site for more information.

Increasing safety is one of our priorities
Safety for the public and the construction workers is paramount while the work is underway.  A comprehensive traffic control plan will be prepared to protect travelers and workers.

Will this project impact tribal resources?
No impacts have been identified.  WSDOT addresses the concerns of tribal nations using the process outlined in Section 106 of the National Historic Preservation Act and WSDOT Tribal Consultation Policy adopted in 2003 by the Transportation Commission as part of the WSDOT Centennial Accord Plan.

Financial Information
This project was advertised for private contractor bids on April 7, 2008. Two qualified bids were opened on May 8th. Contract #7539 was awarded on May 12th to Granite Northwest, Inc., dba Basin Asphalt for $1,239,239.00, 20% under the engineering estimate.

This project is funded through the following sources: 

  • Pre-Existing Gas Tax - $4.09 million
  • Total funding from all sources - $4.09 million

How can I get more information?
Contact:
Project Engineer Kevin Waligorski
WSDOT North Central Region
P.O. Box 98
Wenatchee, WA 98807
Phone:  (509) 667-2860 or toll free (888) 461-8816
Email: waligok@wsdot.wa.gov

back to top