SR 270 - Pullman to Idaho St Line - Additional Lanes

Quarterly Project Report Update for Quarter Ending March 2005

Project Title & Location
SR 270/Pullman to Idaho State Line.   East of Pullman in Whitman County.

Project Description
As Revised September 2004 - Constructs one additional lane in each direction with a two way turn lane between Pullman and the Idaho State line. The project will increase capacity and reduce travel times. Safety will be enhanced with the addition of a two way turn lane to provide separation between opposing directions of traffic. There are currently two lanes. There will be four through lanes when this project is completed.

Contractor/Consultant
Project not yet advertised or awarded

Recent Progress

(As Revised September 2004)
This project constructs a four-lane highway, with a continuous center turn lane, along the existing SR 270 alignment.  Development of environmental documentation in relation to wetlands and water quality issues has been completed and an environmental permit (known as a JARPA) submitted to Regulatory Agencies for approval.  Contract plan preparation is approximately 60% complete.  Right of way for thirteen of 27 parcels has been acquired.  The Department has reached agreement on four of the remaining 14 parcels.

Design Construction Impacts

At this time there are no impacts to the project as updated in the September 2004 Gray Notebook.

Environmental Impacts / Compliance

The Joint Aquatic Resources Permit Application (JARPA) has been submitted to the regulatory agencies with final approval expected just prior to the revised contract ad date. 

Impacts to Traffic
No significant impacts expected until the project is under construction.  Mitigation efforts include a comprehensive public awareness campaign.

Project Milestones Scheduled Attained Milestone Outlook
Start Project July 2003 July 2003  
Environmental Document October 2005   The revised schedule is tightly tied to the attainment timeline for permits.  
Right of Way October 2005   Right-of-way appraisals and offers continue (13 of 27 parcels have been settled).
Contract Ad November 2005  

Previously noted revisions to the project have delayed the original Ad date by 10 months to November 2005.

Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 4.2 14.0%
Right-of-Way $ 6.3 21.1%
Construction $ 19.4 64.9%
Funded Project Costs $ 29.9 100%

Nickel funds included in above costs

$28.5 95.3%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Glenn Wagemann, WSDOT Project Engineer @ (509) 324-6251 Or E-mail wagemag@wsdot.wa.gov