SR 26 - Intersection Illumination

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location
SR 26/Othello Vicinity - Install Lighting

Project Description
This project will install streetlights on SR 26. This will reduce the risk of nighttime collisions at the intersections with B SE and Reynolds Road.

Contractor/Consultant
This project has not be advertised or awarded.

Recent Progress
Illumination at B SE is being included in the NCR 2008 Seal and will be constructed in the spring of 2008.  Illumination of Reynolds Road will be delayed by one year to coincide with a developer project at the intersection.  This will impact the operationally complete date.

Design Construction Impacts
Impacts to surrounding property owners will be minimal.  No right of way acquisition is anticipated.

Environmental Impacts / Compliance
Environmental documentation will be tied with NCR 2008 Seal and developer project.

Impacts to Traffic
Traffic impacts will include one-way flagger controlled traffic during construction.

Project Milestones Scheduled Attained Milestone Outlook
Project Definition Complete May 8, 2006 May 8, 2006 Complete
PE Phase Start July 3, 2007 May 3, 2007 Complete
Environmental Documentation Complete January 31, 2008 No issues at this time.
Ad Date April 14, 2008 No issues at this time.
Operationally Complete December 1, 2008 Will be delayed to tie illumination at Reynolds road with developer work.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering .080 41
Right-of-Way 0
Construction .113 59
Funded Project Costs 0.193 100

Nickel funds included in above costs

0 0

2005 Transportation Partnership Account

0.193 100

  For more information, go to www.wsdot.wa.gov/projects