SR 240 - Yakima River Bridge - Complete June 2007

Quarterly Project Report Update for Quarter Ending December 2005

Project Title & Location

SR 240 / Yakima River Bridge at Richland (Phase 2)

Project Description
Construct two new bridges on SR 240 to replace the deficient four-lane bridge over the Yakima River. New bridges will each provide three general-purpose lanes and one auxiliary lane. The new bridges will tie in with the additional lanes to be constructed on SR 240 between I-182 and Columbia Center Boulevard, which are scheduled for completion in 2007.

Contractor/Consultant
 Wildish Standard Paving Co, dba F. E. Ward Constructors, Inc. - Vancouver, WA

Recent Progress
Work resumed on October 3, 2005.  Due to the suspension of work, for more favorable weather that will ensure higher plant survivability, the project completion was pushed to November 2005.   All planting has been completed This project received substantial completion on October 28, 2005, and is on schedule and under budget

Design Construction Impacts
WSDOT is continuing to work with the contractor on the change order reducing work by about $749,000 on this project due to the adjacent SR 240 Add Lanes project.

Environmental Impacts / Compliance
Construction and planting at Mitigation Site 1, 2 and 3 is complete.

The south 220 feet of the realigned ditch will be realigned on the adjacent contract.

Impacts to Traffic
There will be no more impacts to traffic.

The portions of the existing bike path under the bridge has been opened.  The bike path across the 240/12N bridge will not be opened until remainder of the SR 240 corridor work is completed in 2007.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised  Oct 2002  Feb 2003  Environmental documentation for the corridor project took longer than expected.  Region separated bridge project from corridor project in order to make a 2003 Ad date.
Contract Awarded  Apr 2003 Apr 2003 Completed as scheduled.
Groundbreaking  May 2003 May 2003 Completed as scheduled.
Open Stage 1 Bridge to Traffic May 2004  Aug 2004

With the completion of Stage 1 Bridge, all traffic will be detoured onto Bridge 240/12S.  Traffic will remain in this configuration at the completion of this project.  Delays due to harsh winter weather conditions.

 Contract Complete Aug 2005 Nov 2005  No impacts anticipated at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering  $2.1   9.1%
Right-of-Way  $0.2  0.9%
Construction  $20.6  90.0%
Funded Project Costs  $22.9  100.0%

Nickel funds included in above costs

 N/A  N/A

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Moe Davari, WSDOT Project Engineer @ (509)-222-2402