SR 240 - Beloit Rd to Kingsgate Way - Widen Roadway

Quarterly Project Report Update for Quarter Ending December 2008

Project Title & Location
SR 240 - Beloit Rd to Kingsgate Way - Widen Roadway

Project Description
The section of SR 240 from Beloit Road to Kingsgate Way has experienced a number of serious collisions. Widening the roadway to 12 ft lanes with 8 ft shoulders will improve the safety of the highway and provide more recovery area.

Contractor/Consultant
N/A

Recent Progress
The plans are complete and the Ad date is scheduled for February 9th.

Design Construction Impacts
None

Environmental Impacts / Compliance
None

Impacts to Traffic
None

Project Milestones Scheduled Attained Milestone Outlook
PE Phase Start November 05 March 06
Environmental Document Complete April 08
Right of Way Certified October 08 None anticipated at this time.
Contract Advertisement Date January 09 No impacts anticipated at this time.
Operationally Complete November 09 No impacts to the schedule anticipated
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  2.0 12 %
Right-of-Way $  0.5  3 %
Construction $ 14.4 85 %
Funded Project Costs $ 16.9 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 16.9 100 %

  For more information, go to www.wsdot.wa.gov/projects

Moe Davari, WSDOT Project Engineer

(509) 222-2402,  davarim@wsdot.wa.gov

Project Cost Summary and Scheduled Project Milestones reflect the April 2008 Approved Legislative Budget.