SR 240 - Beloit Rd to Kingsgate Way - Widen Roadway - Complete July 2010

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location
SR 240 - Beloit Rd to Kingsgate Way - Widen Roadway

Project Description
The section of SR 240 from Beloit Road to Kingsgate Way has experienced a number of serious collisions. Widening the roadway to 12 ft lanes with 8 ft shoulders will improve the safety of the highway and provide more recovery area.

Contractor/Consultant
N/A

Recent Progress
Preliminary plans production continues.  The cultural resources consultation has begun with the tribes and the environmental documentation process has begun.  Design is continuing as scoped with modified cut and fill slopes within the culturally sensitve areas to minimize impacts.

Design Construction Impacts
None

Environmental Impacts / Compliance
None

Impacts to Traffic
None

Project Milestones Scheduled Attained Milestone Outlook
PE Phase Start November 05 March 06
Environmental Document Complete April 08 The environmental office has rescoped the project for the new scope change. 
Right of Way Certified October 08 None anticipated at this time.
Contract Advertisement Date January 09 No impacts anticipated at this time.
Operationally Complete November 09 No impacts to the schedule anticipated
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  2.0 12 %
Right-of-Way $  0.5  3 %
Construction $ 14.4 85 %
Funded Project Costs $ 16.9 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 16.9 100 %

  For more information, go to www.wsdot.wa.gov/projects

Moe Davari, WSDOT Project Engineer

(509) 222-2402,  davarim@wsdot.wa.gov

  

Project Cost Summary reflects the March 2006 Approved Legislative Supplemental Budget