SR 240 - Beloit Rd to Kingsgate Way - Widen Roadway

Quarterly Project Report Update for Quarter Ending December 2006

Project Title & Location
SR 240 - Beloit Rd to Kingsgate Way - Widen Roadway

Project Description
The section of SR 240 from Beloit Road to Kingsgate Way has experienced a number of serious collisions. Widening the roadway to 12 ft lanes with 8 ft shoulders will improve the safety of the highway and provide more recovery area.

Contractor/Consultant
N/A

Recent Progress

Accident History has been reviewed and an alternative design that changes the scope of the project has been developed that would improve safety for 18 miles by widening the narrow roadway to 12 ft lanes and 8 ft shoulders with rumble strips.  This alternative will be presented to the Legislature during the next legislative session for approval.  Two surveying crews continue to gather topographical information and are likely to continue collecting data into January.  The project schedule still reflects the original scope of work. 

Design Construction Impacts
None

Environmental Impacts / Compliance
None

Impacts to Traffic
None

Project Milestones Scheduled Attained Milestone Outlook
PE Phase Start November 05 March 06
Environmental Document Complete April 08 The environmental office is set to rescope the project for the new scope change once the topographical survey is complete. 
Right of Way Certified September 08 None anticipated at this time.
Contract Advertisement Date October 08

No impacts anticipated at this time.

Operationally Complete November 09 No impacts to the schedule anticipated
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  2.0 12.1 %
Right-of-Way $  0.5  3.0 %
Construction $ 14.0 84.9 %
Funded Project Costs $ 16.5 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 16.5 100 %

  For more information, go to www.wsdot.wa.gov/projects

Moe Davari, WSDOT Project Engineer

(509) 222-2402,  davarim@wsdot.wa.gov

  

Project Cost Summary reflects the March 2006 Approved Legislative Supplemental Budget