SR 24 - SR 241 to Cold Creek Rd - Add Passing Lanes - Complete August 2008

Quarterly Project Report Update for Quarter Ending March 2006

Project Title & Location
SR 24 - SR 241 to Cold Creek Road - Added Lanes

Project Description
This project will construct a passing lane uphill in both directions on SR 24 between SR 241 and Cold Creek Road. Constructing a passing lane will improve safety, reduce collisions, and increase traffic mobility.

Contractor/Consultant

Recent Progress
Work on this project is anticipated to start in April or early May. 

Design Construction Impacts
No impacts are anticipated at this time.

Environmental Impacts / Compliance
No impacts are anticipated at this time.

Impacts to Traffic

Project Milestones Scheduled Attained Milestone Outlook
PE Phase Start November 05
Environmental Document Complete December 06
Right of Way Certified September 07
Contract Advertisement Date October 07
Operationally Complete October 08
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 0.6 14.1 %
Right-of-Way $ 0.2  4.7 %
Construction $ 3.5 81.2 %
Funded Project Costs $ 4.3 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 4.3 100 %