SR 24 - I-82 to Keys Rd - Add Lanes - Open June 2007

Quarterly Project Report Update for Quarter Ending June 2007

Project Title & Location
SR 24 - I-82 to Keys Road - Additional Lanes - Yakima

Project Description
This project constructs one additional lane in each direction from I-82 to Riverside Road, improves the interchange, and constructs a new bridge over the Yakima River, relieving congestion, improving safety, and addressing erosion at the Yakima River Bridge piers.

Contractor/Consultant
Max J. Kuney of Spokane WA

Recent Progress
The contractor, Max J. Kuney has completed the roadway work this quarter, giving traffic full use the new roadway. WSDOT hosted a ribbon cutting ceremony on June 28, 2007 to celebrate the opening of the roadway to traffic. 
The contractor started the process to remove the old bridge over the Yakima river on June 1st at the start of the fish window.  Work continues on roadside features of the highway.
On May 2, 2007 WSDOT dedicated corridor revitalization art work on the project.

Design Construction Impacts
The contractor accelerated roadway work to open new facility to traffic before the 4th of July.

Environmental Impacts / Compliance
Due to recent listing of critical habitat for Mid-Columbia River Steelhead, additional coordination was necessary with the National Marine Fisheries Service prior to beginning 2007 in-water work.  Verbal concurrence was received on June 1, 2007 allowing the contractor to begin in-water work without delay.
The contract office approved a demolition plan for the old SR 24 Bridge that includes primary and secondary containment.  We anticipate minor updates to regulatory permits by the middle of June because of necessary plan changes.
Field inspectors and region environmental staff will closely monitor demolition, and take water quality samples as necessary.

Impacts to Traffic
A lane will be closed on I-82 as needed for construction access. The I-82 lane closure will cause back-ups during high traffic flows. The speed limit is reduced to 35 mph on SR 24 from I-82 to Riverside Road for the life of the project.  When needed, traffic on SR 24 will be controlled by flaggers.  Motorists can expect delays up to five minutes and possible backups.

Project Milestones Scheduled Attained Milestone Outlook
Start Project  Oct 98 Dec 98  
Environmental Document Dec 03  Aug 04  
Environmental Permits Sep 04 Feb 05  The SEPA completion was delayed due to negotiating permit conditions with the City of Yakima.
Contract Advertised Apr 05  Feb 05 This project's advertisement was advanced to Feb 05 to align construction work with the environmental permit conditions.
Open to Traffic Dec 07 June 07  Roadway open to traffic 7 months ahead of schedule.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 3.9 7.7 %
Right-of-Way $ 5.2  10.2%
Construction $41.8 82.1 %
Funded Project Costs $50.9 100 %

Nickel funds included in above costs

$36.4 71.5 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Paul Gonseth, Project Engineer
(509) 577-1810 or gonsetp@wsdot.wa.gov
Project Cost Summary reflects the March 2006 Approved Legislative Supplemental Budget