SR 24 - I-82 to Keys Rd - Add Lanes - Open June 2007

Quarterly Project Report Update for Quarter Ending December 2006

Project Title & Location
SR 24 – I-82 to Keys Road – Additional Lanes – Yakima

Project Description
This project constructs one additional lane in each direction from I-82 to Riverside Road, improves the interchange, and constructs a new bridge over the Yakima River, relieving congestion, improving safety, and addressing erosion at the Yakima River Bridge piers.

Contractor/Consultant
Max J. Kuney of Spokane WA

Recent Progress
The contractor, Max J. Kuney, is near completing the I-82 interchange bridge and the Yakima River bridge, all roadway decks are complete and traffic barrier / utility connection remain.  The contractor has placed traffic in a two lane temporary configuration on the south side of the new SR 24 alignment.  Yakima County 33rd Street extension is paved and open to traffic.

Design Construction Impacts

This project is projected to overrun reimburseable utililty agreements by $150,000.  The contract plans did not clearly define proposed utility locations and conflicts with work after relocations.
Material delivery issues has delayed an early opening of SR 24 roadway.  Final paving and safety features should be completed in the Spring of 2007.

Environmental Impacts / Compliance
This project is currently under review for a possible discharge of sediment as a result of high river flows entering the project site.  The project engineer is currently working with the regulatory agencies to address the issue.  The Department of Ecology reviewed the project and determined that we cannot discharge pH laden water as outlined in the permits. The project cost has increased  $141,000 to dispose of this pH laden water as directed by the Department of Ecology.  Temporary pollution control was under-estimated and will add approximately $600,000 to the project cost.

Impacts to Traffic
A lane will be closed on I-82 as needed for construction access. The I-82 lane closure will cause back-ups during high traffic flows. The speed limit is reduced to 35 mph on SR 24 from I-82 to Riverside Road for the life of the project.  When needed, traffic on SR 24 will be controlled by flaggers.  Motorists can expect delays up to five minutes and possible backups.

Project Milestones Scheduled Attained Milestone Outlook
Start Project   Dec 98  
Environmental Document Dec 03  Aug 04  
Environmental Permits Sep 04 Feb 05  The SEPA completion was delayed due to negotiating permit conditions with the City of Yakima.
Contract Advertised Apr 05  Feb 05 This project's advertisement was advanced to Feb. 05 to align construction work with the environmental permit conditions.
Open to Traffic Dec 07   The roadway will be open to traffic in winter of 2006 in a temporary configuration.  Final roadway work should be completed in the Spring of 2007.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 3.8 7.6 %
Right-of-Way $ 5.1  10.2%
Construction $42.0 82.2 %
Funded Project Costs $50.9 100 %

Nickel funds included in above costs

$36.4 72.5 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Paul Gonseth, Project Engineer
(509) 577-1810 or gonsetp@wsdot.wa.gov