May 2006 - Work continues on the new relocated city street north of SR 24.June 2006 - Construction continues on the new access road to the Humane Society and the Arboretum.July 2006 - Curb, gutter, and sidewalks have been installed, and the new access road to the Arboretum and the Humane Society has been paved.New city street / access to KMart, the Arboretum, and the Humane Society._________________________________________________________New relocated road behind K-MartMay 2006 - New relocated road behind KMart is now complete.Early September 2005.Early September 2005.Late September 2005 - Clearing for a relocated road behind Kmart.Late September 2005 - Clearing for a relocated city street that will provide access to local businesses and Yakima's sewer treatment plant.October 2005 - Paving is complete and curbs are set.October 2005 - Surveying the new relocated road behind Kmart.November 2005 - The new, relocated city street near KMart nearly complete.November 2005 - New relocated road behind KMart nears completion._________________________________________________________November 2005 - Pier construction near the Yakima River Bridge.August 2005 - Staging area west of the Yakima River Bridge.September 2005 - Staging area west of the Yakima River Bridge.