WSDOT Projects

text size: T T T

SR 202 - SR 520 to Sahalee Way - Environmental Work

Widening SR 202 from SR 520 in Redmond to Sahalee Way in rural King County has presented many environmental challenges for our engineers.  The road runs through wetlands, flood plains and even an ancient land slide.

Besides complying with federal and state environmental laws, we are proud of our efforts to be good neighbors and environmental stewards.  We want to leave the environment in a better and more stable condition than before we began this important road widening project.

When we're finished we will have improved drainage, created new and improved wetlands, and built retaining walls to prevent landslides.

Wetland Mitigation

WSDOT has adopted a goal of "no-net-loss" of wetland acreage and function.  In that effort, this project:

  • Creates three flood plain and/or wetland mitigation sites including a 16-acre wetland at the corner of SR 202 and Sahalee Way to make up for land we have to displace to widen the highway.
    • The first site (called the Raab site), located between 188th and 196th Avenues NE, serves for flood mitigation. Crews excavated material in this area to ensure that, in the event of a flood, the elevation of the creek does not rise and create flooding downstream.
    • The second site, at Sahalee Way, provides most of the flood volume storage needed for mitigation of the entire SR 202 widening project. A channel running through this site connects a small tributary to Evans Creek at the northwest corner of the site.
    • The third mitigation site is located at 196th Avenue NE, where we will create a backwater channel for the creek. Excavation at this site begins in August 2007 and planting is scheduled for the winter.  
  • Crews will construct 22 retaining walls totaling roughly 4,000 square feet to help protect Evans Creek, wetlands, floodplains, and properties along the SR 202 corridor.


Work is underway to create a new wetland at the corner of SR 202 and Sahalee Way.  The site of a former dairy farm will replace wetland filled in for widening SR 202.  The project also includes stream restoration for Evans Creek.

Crews constructed a shady area for fish and other wildlife along Evans Creek.
Crews constructed a shady area for fish and other wildlife along Evans Creek in the wetland area in Happy Valley.

n/a
This backwater channel will be a peacful refuge for fish on their journey up Evans Creek. Crews are now adding 7 inches of compost and 3 inches of bark to this area. Between November 2006 and March 2007crews will plant 37,000 plants and several hundred trees.

The entire 16 acre site will be green and lush like this portion of the site that was completed last year.

Improved water quality and erosion prevention

Roadway runoff is an unacceptable source of river and area stream pollution.

  • Crews will improve how water from the roadway is retained, treated and released back into ground by building two underground wet vaults, a pond for water detention and quality treatment and another pond just for detention.
  • We will install two bioswales (landscape structures designed to remove silt and pollution from runoff water).
  • Crews will construct three quarters of a mile of Ecology Embankment, a small grass filter strip followed by a trench backfilled with gravel and other materials.  Ecology Embankment is an experimental water quality treatment that is, basically, a linear storm water treatment facility incorporated into the road embankment rather than a separate pond or wet vault.

Reduced noise

  • Noise walls will be built through a half-mile stretch of SR 202.