SR 202 - Preston Fall City Road and Jct SR 203

Quarterly Project Report Update for Quarter Ending June 2005

Project Title & Location
SR 202 - Jct. Preston-Fall City Road & Jct. SR 203 - at Fall City

Project Description
This project will construct sidewalks and intersection control improvements at the intersection of SR 202 and Preston-Fall City Road and at the intersection of SR 202 and SR 203.

Contractor/Consultant
A Contractor will be selected in Winter 2006.

Recent Progress
Funding was approved to start work in January 2004.  A single lane roundabout has been designed for the intersection of SR 202 and SR 203.   Channelization plans are being developed for approval. 

Design Construction Impacts

The roundabout design will require right of way from three existing businesses which may result in a total acquisition of the property.  

Environmental Impacts / Compliance
Construction of the roundabout will result in flood plain compensatory storage impacts.  The flood plain mitigation is planned to be mitigated on existing right of way and at an adjacient project site.  Endangered Species and water quality are being addressed in the project.   Detention is not required.

Impacts to Traffic
Intermittent lane closures are expected during the construction of this project (2007 and 2008).

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering July 2005   Roundabout design is in review.  Challenges are being experienced in trying to find a design that will operate well and stay within budget for environmental constraints, right of way and construction.
Environmental Document Complete September 2006 Good
Right of Way Certification September 2006 The right of way plan is planned to be submitted for Region review in June. 
Advertisement October 2006 Good
Open to Traffic November 2007 Good
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.62 m 21.5%
Right-of-Way $0.83 m 28.7%
Construction $1.44 m 49.8%
Funded Project Costs $2.89 m 100%

Nickel funds included in above costs

$2.50 m 86.5%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

 

David Edwards, WSDOT Project Engineer @ (206) 440-4312

or E-mail: edwardd@wsdot.wa.gov