SR 202 - Preston Fall City Road and Jct SR 203 - Complete July 2008

Quarterly Project Report Update for Quarter Ending December 2005

Project Title & Location
SR 202 - Jct. Preston-Fall City Road & Jct. SR 203 - at Fall City

Project Description
This project will construct sidewalks and intersection control improvements at the intersection of SR 202 and Preston-Fall City Road and at the intersection of SR 202 and SR 203.

Contractor/Consultant
A Contractor will be selected in Winter 2006.

Recent Progress

A single lane roundabout has been designed for the intersection of SR 202 and SR 203. The draft channelization plans have been reviewed and comments are being addressed.   The project drainage requirements for water quality and floodplain impacts have been defined for the project.   Detention is not required for the project.

A draft Hazardous Waste Report has been completed for the property acquisition area. 

Design Construction Impacts

The roundabout design will require right of way from three existing businesses on one parcel which may result in a total acquisition of the property.  

Environmental Impacts / Compliance

The roundabout has been designed so that the cuts and fills within the flood plain balance out.  The Design Office is working with the WSDOT HQ Hydraulics and King County staff to complete the Floodplain impact documentation requirements. 

The draft Hazardous Waste report has confirmed that an old gas station tank was previously removed from the property.  Additional investigation has been recommended to confirm if any soil contamination still remains. 

A Section 106 report for possible archaeological artifacts is being completed.  A previous report on an adjacent project indicated the possibility of artifacts in the area however no artifacts were found during construction.

Impacts to Traffic
Intermittent lane closures are expected during the construction of this project (2007 and 2008).

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering July 2005   Roundabout design is in review.  The current design is expected to operate well and is currently within the available construction budget for the project.  The Preliminary Engineering budget is currently within budget but may experience an overrun if environmental issues require additional budget to complete.
Environmental Document Complete September 2006 Good
Right of Way Certification September 2006 The right of way plan is being reviewed in Headquarters.  Plan approval is anticipated to be early September 2005.
Advertisement October 2006 Good
Open to Traffic November 2007 Good
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.62 m 21.5%
Right-of-Way $0.83 m 28.7%
Construction $1.44 m 49.8%
Funded Project Costs $2.89 m 100%

Nickel funds included in above costs

$2.50 m 86.5%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

 

David Edwards, WSDOT Project Engineer @ (206) 440-4312

or E-mail: edwardd@wsdot.wa.gov