SR 20 - Fredonia to Interstate 5 - Additional Lanes

Quarterly Project Report Update for Quarter Ending December 2003

Project Title & Location

SR 20 Fredonia to I-5

Located on SR 20 in Skagit County near Burlington.

Project Description
This project will improve approximately 5 miles of State Route 20 in Skagit County, from the intersection of SR 536 (Fredonia) to Interstate 5 (Burlington). This portion of SR 20 is currently a two-lane undivided highway, which this project would upgrade to a four-lane divided highway. In addition, realignment of the southbound I-5 ramps and modifications to the northbound ramps will improve movement at the SR 20/I-5 interchange.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress

· Value Engineering study held in October.
· Wetland Impacts determined

Design Construction Impacts

· Updating the roadway geometrics to meet current guidelines, traffic report recommendations and Value Engineering study conclusions.

· Working on the Access Point Decision Report, Access hearing plans and Right of Way plans.

Environmental Impacts / Compliance

· Updating discipline studies.
· Locating a wetland mitigation site that will accommodate project impacts to wetlands.

Impacts to Traffic

· Moderate impacts to daily traffic due to normal construction activities (trucks entering and exiting the roadway etc.).

· Significant short-term impacts will occur during new roadway and ramp connections. 

Project Milestones Scheduled Attained Milestone Outlook
Environmental Documentation June 2004 Locating an adequate wetland mitigation site is critical to the schedule.
Begin Right-of-Way Acquisition July 2004 Access hearing still scheduled for April.
Contract Advertisement Oct 2006
Begin Construction Spring 2007
Open to Traffic Summer 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $5.0 m 6.2%
Right-of-Way $14.0 m 17.2%
Construction $62.4 m 76.6%
Funded Project Costs $81.5 m 100%

Nickel funds included in above costs

$76.3 m 93.6%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects