Design Construction Impacts
· The project has been broken into three stages due to $22 million in funding shortfalls resulting from increase in real estate values, general cost escalations, and increase in agreement costs. Stage 1 and 2 are funded for construction. However, Stage 3 is not funded for construction. Stage 1 provides improvements from the SR 536 interchange to east of Higgins Airport Way. Stage 2 provides improvements from Pulver Road to the SR 20/I 5 interchange. Stage 3 is located between Stage 1 and 2 limits and provides improvements from west of Avon Allen Road to Pulver Road.
· The State will be acquiring the additional Right of way for the City of Burlington for their Nevitt Road project. This will eliminate multiple property acquisition transactions with property owners. The start of negotiations in the vicinity of the interchange has been delayed as right of way plans are updated.
· This project changes access rights and traffic movements to right-in/right-out only for all properties adjacent to the highway.
|