|
Design Construction Impacts
· Delays in the Access Hearing process have caused a delay to the start of right of way acquisition. As a result, the October 2006 bid advertisement date is at risk of being delayed. To mitigate for schedule delays, as reported in June 2005, the Department is proposing to construct the project under two stages. Under this proposal, stage one would begin at the SR 536/SR 20 intersection and continue past the Higgins/Airport Way intersection. The ad date for Stage one would be October 23, 2006. Stage two would construct the remainder of the project improvements and would go to bid advertisement in January 2008.
· Right of way acquisition for nine properties within Stage 2 are currently being affected by two appeals to the Access Hearings Findings and Order.
· Wetland bank site has not yet been approved by permitting agencies. Looking into developing wetland mitigation site elsewhere.
· This project changes access rights and traffic movements to residential, farm, and commercial property.
|