SR 20 - Fredonia to Interstate 5 - Additional Lanes

Quarterly Project Report Update for Quarter Ending June 2004

Project Title & Location

SR 20 Fredonia to I-5

Located on SR 20 in Skagit County near Burlington.

Project Description
This project will improve approximately 5 miles of State Route 20 in Skagit County, from the intersection of SR 536 (Fredonia) to Interstate 5 (Burlington). This portion of SR 20 is currently a two-lane undivided highway, which this project would upgrade to a four-lane divided highway. In addition, realignment of the southbound I-5 ramps and modifications to the northbound ramps will improve movement at the SR 20/I-5 interchange.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress

· Access hearing plans in for Regional review.

· Completed geometric design based on current guidelines, traffic report,  recommendations from Value Engineering study.

 · Started 21 parcel acquisitions where complete parcel is needed.

 · Noise study completed, Hazardous Materials study complete, Biological assessment completed, and supplemental traffic study completed.

Design Construction Impacts

· Purchase of residential, farm, and commercial property.

· Changing of access rights and traffic movements to residential, farm, and commercial property.

Environmental Impacts / Compliance

· Updating discipline studies.
·Determined that project has 7.79 acres of wetland impact.  Will require 15.58 acres of wetland mitigation. Looking at using wetland banking as a possibility for mitigating wetland impacts.

Impacts to Traffic

· Moderate impacts to daily traffic due to normal construction activities (trucks entering and exiting the roadway etc.).

· Significant short-term impacts will occur during new roadway and ramp connections. 

Project Milestones Scheduled Attained Milestone Outlook
Environmental Documentation June 2004 Locating an adequate wetland mitigation site is critical to the schedule.
Begin Right-of-Way Acquisition September 2004 Access hearing scheduled for end of August.
Contract Advertisement Oct 2006
Begin Construction Spring 2007
Open to Traffic Summer 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $5.0 m 6.2%
Right-of-Way $14.0 m 17.2%
Construction $62.4 m 76.6%
Funded Project Costs $81.5 m 100%

Nickel funds included in above costs

$76.3 m 93.6%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Randy Simonsen, WSDOT Project Engineer @ (425) 744-5102; or SimonsR@wsdot.wa.gov