Design Construction Impacts
· The project has been broken into three stages due to funding shortfalls resulting from increases in real estate values, general cost escalations, and increase in agreement costs. Stage 1 and 2 are funded for construction in 2007 and 2008, and Stage 3 is funded for construction in 2017. Stage 1 provides improvements from the SR 536 interchange to east of Higgins Airport Way. Stage 2 provides improvements from Pulver Road to the SR 20/I 5 interchange. Stage 3 is located between Stage 1 and 2 limits and provides improvements from west of Avon Allen Road to Pulver Road.
· The State will be acquiring additional Right of Way for the City of Burlington for their Nevitt Road project on those parcels that the State was already planning a partial take. This will eliminate multiple property acquisition transactions with property owners.
· This project changes access rights and traffic movements to right-in/right-out only for all properties adjacent to the highway.
|