Loup Loup Pass Emergency Repair 2017 Phase 2 - Photos

Friday April 7 morning mudslide SR 20

It started like this. A relatively small mudslide on SR 20 near Loup Loup summit on Friday morning, April 7.
Then, a few hours later and...

Friday April 7 MP 222 washout SR 20

One washout location On  at MP 222 on Friday afternoon April 7

By the following week, the damage locations had grown to eight.

April 19 photo & Map of 8 damage locations

This May 19 progress photo  at MP 222 shows the rebuilding work accomplished in a month

May 19 Progress MP 221 SR 20

On June 9 work to rebuild MP 211 was moving ahead.

June 9 Progress MP 211.85 SR 20

By late July, repairs to 7 of the 9 locations were complete.  Portable traffic signals controlled traffic at MP 221 - 6 miles east of Loup Loup summit where work continued.
MP 221 Temporary Signals July 25