Recent Progress
· Project wetland impacts have been identified and Wetland/Biology Report is complete.
· Stage 1 Right of Way plans are being developed and will be completed in September.
· Design started for Fidalgo Bay wetland mitigation site.
·Stage 1 hydraulic design is 85% complete.
·The Biological Assessment is complete and has been submitted to the agencies for review.
·The Environmental Justice Memo is complete and submitted for review.
·Coordination with the Samish Tribe has been ongoing and progress was made in identifying the documents needed to present our right of way needs to the Tribal Council.
·Two consultant agreements were finalized. One agreement will authorize the consultant to complete the hydraulics plan for Stage 2. The other agreement will be for a right of way plan for Stage 2.
·The design office is preparing information to present to the public that describes the reasons for the proposed closure of three County Road intersections on SR 20.
|