|
Project Title & Location
Quiet Cove Road Vicinity to SR 20 Spur Vicinity. SR 20 in rural Skagit County near Lake Campbell.
|
Project Description
This project will construct safety improvements along SR 20 by grading and widening. Left turn lanes will be constructed at Lunz/Deception Road. A new bridge will be constructed over Meadow Creek to accommodate the left turn lanes and provide fish passage.
|
|
Contractor/Consultant
Project not yet advertised or awarded
|
|
Recent Progress
· Held Round Table Meeting. · Received proof copy comments for Stage 1 Plans, Specifications and Estimate. · Environmental permitting applications in process with permitting agencies. · Final hydraulics report comments addressed and report submitted. · Completing acquisition of property for wetland mitigation site and remaining right of way necessary for Stage 1construction. · The right of way acquisition for Stage 2 is in progress. · Coordination with the Samish Tribe is ongoing. · Hearing for Anacortes Shorline Permit was held. The City Council gave project approval. · Construction Permits and bicycle detour agreement received from the City of Anacortes.
|
|
Design Construction Impacts
· Three Stage 1 right of way acquisitions proceeding to condemnation. If possession and use of the properties is not secured by mid March, the advertisement date will need to be delayed. · As reported in previous quarters, project costs have increased. Construction of Stage 2 may need to be deferred if an additional $9.8 million is not appropriated in the new 2007 legislative budget. · There are existing utility easements adjacent to State right of way that will be impacted by this project. A portion of the utility relocation costs will be the responsibility of the WSDOT.
|
|
Environmental Impacts / Compliance
Wetland impacts have been minimized. New wetlands will be built to mitigate for wetland impacts. We will adhere to permit requirements.
|
Impacts to Traffic
Significant impacts will occur when construction takes place in the summer of 2007 and 2008 · There will be a public information campaign to alert the public to future traffic impacts.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Environmental Documentation Complete
|
Jan 2005
|
July 2006
|
Environmental documentation complete for Stage 1 and 2. Environmental permitting in progress.
|
|
Right of Way Certified Stage 1/Right of Way Certified Stage 2
|
April 2007/February 2008
|
|
Stage 1 Right of Way acquisitions nearing completion with exception of three parcels proceeding to condemnation. Stage 2 Right of Way acquisition in process.
|
|
Contract Advertisement Stage 1/Contract Advertisement Stage 2
|
April 2007/February 2008
|
|
Contract Advertisement delayed until May 7, 2007 due to right of way acquisition difficulties and problems obtaining needed environmental permits.
|
|
Open to Traffic Stage 1/Open to Traffic Stage 2
|
October 2008/October 2009
|
|
|
|
|
|
|
|