|
Design Construction Impacts
Retaining walls will be constructed to minimize impacts to forrested wetlands and to mitigate unstable slopes. Construction of a temporary alignment will be needed to accomodate bridge construction.
A Cost Risk Assessment (CRA) workshop performed in April 2004 and subsequent in depth reviews of the results have identified a new total project cost of $18.3 million, an increase of $3.8 million. The project team is proposing to stage the project to offset the budget shortfall. Under this proposal, design and right of way acquisition for the entire project and construction of Stage 1, defined as the 1.42 mile section from the Quiet Cove vicintiy to the North Campbell Lake Road vicinity, would be funded with the original legislative allocation. Construction of stage 2, defined as the 1.8 mile section from the North Campbell Lake Road vicinity to the junction of the SR 20 Spur, is not funded.
|