Project Title & Location
Quiet Cove Road Vicinity to SR 20 Spur Vicinity. SR 20 in rural Skagit County near Lake Campbell.
|
Project Description
This project will construct safety improvements along SR 20 by grading and widening. Left turn lanes will be constructed at Lunz/Deception Road. A new bridge will be constructed over Meadow Creek to accommodate the left turn lanes and provide fish passage.
|
|
Contractor/Consultant
Stage 1 of project advertised but not yet awarded. Stage 2 has not been advertised.
|
|
Recent Progress
· Stage 1 is on AD. · All environmental permits received except Skagit County Shoreline permit (needed only for Stg. 2) · Hydraulics report for Stage 1 approved. · Property for wetland mitigation site acquired. · Right of way for Stage 1 certified. · The right of way acquisition for Stage 2 is in progress. · Coordination with the Samish Tribe is ongoing. · Utility relocation for stage 1 being coordinated through design and construction offices · A consultant is being hired to prepare the hydraulics report for Stage 2. The scope of work is being reviewed.
|
|
Design Construction Impacts
· Two new septic drainfields need to be constructed to replace two that will be impacted by construction. · Utility Relocation work will continue during the construction phase of Stg.1. · There are existing utility easements adjacent to State right of way that will be impacted by this project. A portion of the utility relocation costs will be the responsibility of the WSDOT.
· Acquisition of parcel 1-22115 on Samish tribal land is critical to meet the Ad date. This land is currently in trust and must be acquired through the BIA.
|
|
Environmental Impacts / Compliance
Wetland impacts have been minimized. New wetlands will be built to mitigate for wetland impacts. We will adhere to permit requirements.
|
Impacts to Traffic
Significant impacts will occur when construction takes place in the summer of 2007, 2008, and 2009 · There will be a public information campaign to alert the public to future traffic impacts.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Environmental Documentation Complete
|
Jan 2005
|
July 2006
|
Environmental documentation complete for Stage 1 and 2. Environmental permitting in progress.
|
|
Right of Way Certified Stage 1/Right of Way Certified Stage 2
|
April 2007/January 2008
|
May 2007(Stage 1)
|
Stage 1 Right of Way acquisitions complete with exception of three parcels proceeding to condemnation. Possesion and use for Stage 1 parcels in condemnation obtained. Stage 2 Right of Way acquisition in process.
|
|
Contract Advertisement Stage 1/Contract Advertisement Stage 2
|
April 2007/February 2008
|
May 2007(stage 1)
|
Contract Advertisement delayed until May 7, 2007 due to right of way acquisition difficulties and problems obtaining needed environmental permits.
|
|
Open to Traffic Stage 1/Open to Traffic Stage 2
|
October 2008/October 2009
|
|
|
|
|
|
|
|