|
Design Construction Impacts
· Project costs are continuing to increase. Recent update of the estimates for all phases of this project indicates $8.7 million is needed above current funding allocations to construct the entire project. If additional funding can not be obtained, design and right of way acquision will be completed for both stages and Stage 1 constructed. Remaining project funds would go toward constructing improvements in the vicinity of Almida Vista Lane. The remaining Stage 2 improvements will be constructed when additional funding is secured. Increased costs are associated with an increase in materials costs, increase in right of way acquisition costs, and an increase in Stage 2 costs associated with an area south of Gibraltar Road. The area south of Gibraltar Road will require additional areas of rock blasting, construction staging and detour bypasses through the rock blasting area and a forested wetland.
· There are existing utility easements adjacent to State right of way that will be impacted by this project. A portion of the utility relocation costs will be the responsibility of the WSDOT.
|