SR 20 - Quiet Cove Road Vicinity to SR 20 Spur

Quarterly Project Report Update for Quarter Ending December 2005

Project Title & Location

Quiet Cove Road Vicinity to SR 20 Spur Vicinity.

SR 20 in rural Skagit County near Lake Campbell.

Project Description
This project will construct safety improvements along SR 20 by grading and widening. Left turn lanes will be constructed at Lunz/Deception Road. A new bridge will be constructed over Meadow Creek to accommodate the left turn lanes and provide fish passage.

Contractor/Consultant
Project not yet advertised or awarded

Recent Progress

 

 · The the right of way plans being developed by a consultant for stage 2 are 80% complete.  Completion of the plans has been delayed by problems obtaining the needed title reports.

· Stage 1 Right of Way plans have been developed and submitted for review.

· Design of Fidalgo Bay wetland mitigation site is 50% complete.

·Stage 1 hydraulic design is 85% complete.  The conceptual design for stage 2 is complete.

·Applications for all environmental permits will be submitted this Spring. 

·More geotechnical exploration was performed near Lake Campbell to identify the location and quantity of bed rock that will have to be removed for shoulder and lane widening.

·Coordination with the Samish Tribe has been ongoing.  A special right of way plan was developed and submitted for review by the design office to address right of way needs that impact tribal land.  When approved the plan will be presented to the Samish Tribal Council.

·The design office prepared information to present to the public that describes the reasons for the proposed closure of three County Road intersections on SR 20.  Mount Baker administration is coordinating with Skagit County to gain approval for the closures.

Design Construction Impacts

·     In May 2005, the proposed December 2004 project staging and funding shifts for stage 1 were approved. Stage 2 was also funded by the legislature.  Since this time, complications found during preparation of the Record of Survey and hydraulic design have delayed the start of right of way acquisition for Stage 1 and have delayed the advertisement date five months.  Recently, tribal land necessary for project improvements within Stage 1 have been applied for transfer into Trust.  Right of way acquisition of the tribal land is a lengthy process that will cause additional delay to the ad date.  Further, Stage 2 will not be able to meet the approved ad date due to insufficient time for right of way acquisition and time necessary for the City of Oak Harbor and City of Anacortes to design and obtain funding for necessary waterline relocations.  To mitigate for project delays, WSDOT is proposing to change the staging limits.  Under this proposal, stage one limits would be changed to include the southerly project limits, beginning in the vicinity of Meadow Creek and extend just south of the intersection of South Campbell Lake Road.  The ad date for Stage one would be delayed to April 2, 2007 and construction would begin in Spring 2007 as planned.  Stage two would construct the remainder of the project improvements, which include the area in the vicinity of the tribal land and would be advertised in February 2008.

·     Retaining walls will be constructed to minimize impacts to forested wetlands and to mitigate unstable slopes.  Construction of a  temporary alignment will be needed to accommodate bridge construction.

 

Environmental Impacts / Compliance
Weltand impacts have been minimzed.  New wetlands will be built to mitigate for wetland impacts.  We will adhere to permit requirements.

Impacts to Traffic
Significant impacts will occur when construction takes place in the summer of 2007 and 2008 · There will be a public information campaign to alert the public to future traffic impacts.

Project Milestones Scheduled Attained Milestone Outlook
Environmental Documentation Complete Jan 2005 The environmental documentation for the project will be submitted in February 2006.  Complications with utility impacts and the greater than expected number of sensitive areas delayed the submittal of the documentation.
Right of Way Certfied Oct 2006 Complications found during preparation of the Record of Survey and hydraulic design have delayed the start of right of way acquisition.
Contract Advertisement Nov 2006 Delays in the start of right of way acquisition have delayed Stage 1 ad date to April 2007.  Stage 2 ad date is delayed to February 2008 due to delays in right of way acquisition and funding for waterline relocations.
Open to Traffic October 2008 Open to Traffic date may slide to Summer 2009 due to delays in beginning Stage 2 construction.
   
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $3.15 m 17.2%
Right-of-Way $2.92 m 16.0%
Construction $12.21 m 66.8%
Funded Project Costs $18.28 m 100%

Nickel funds included in above costs

$10.91 m 59.7%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Dawn Yankauskas, WSDOT Project Engineer @ (425) 744-5103; or Yankadr@wsdot.wa.gov