Overview
WSF improved the terminal area to make it more user-friendly for pedestrians and vehicles by providing sidewalks and signage to direct pedestrians along a route that is clear of vehicle traffic.
 | Improves Safety
This project provided more space for pedestrians to stand and separated pedestrians from vehicles.
|
 | Relieves Congestion
This project reduces the risk of vehicle/pedestrian conflict and improves ferry loading efficiency.
|
Partnerships & Cooperation
Contractor Strider Construction Co., Inc. performed this work.
Funding
- Budget: $302,790
- Funding: This project is partially funded (80/20 split) by a federal grant received by WSF. The total budget is $302,790 of which $240,790 is federal. The remainder is state.
Contact Us
Joy Goldenberg - WSF Communications Manager
206-515-3411
joy.goldenberg@wsdot.wa.gov
Nicole McIntosh - WSF Terminal Design Engineering Manager
206-515-3714
nicole.mcintosh@wsdot.wa.gov
back to top