SR 18 - Issaquah Hobart Road to I-90

Quarterly Project Report Update for Quarter Ending December 2006

Project Title & Location
SR18 - Issaquah/Hobart Rd to I-90 -  Maple Valley to Snoqualmie

Project Description
This project will complete the environmental work for widening SR 18 to 2 lanes each direction with truck climbing lanes between Issaquah/Hobart Road and I-90, constructing a new interchange at Tigergate summit and making improvements to the I-90/SR 18 interchange.

Contractor/Consultant
Consultant - HDR Engineering

Recent Progress

Preferred alternative and alignment selected for the I-90/SR 18 interchange.  Completed study to identify component and planning alternatives that may offer cost benefits or improve project quality. Continuing work on corridor level route development plan and SR 18/I90 interchange improvement analysis for Federal Highway Administration approval.

Design Construction Impacts

Construction phase not yet funded.  Please see the project page for more information.

Environmental Impacts / Compliance
The project is in early stages of the environmental documentation process.  During this process, the design team will identify project impacts and address compliance issues.

Impacts to Traffic
The completed SR 18 project will improve traffic flow and safety on the highway.

Project Milestones Scheduled Attained Milestone Outlook
Select Consultant August 2003 August 2003 Milestone is complete.
Circulate Documented CE July 2006 Delay due to difficulty in physically gathering field information and longer review times for Endangered Species Act consultation by US Department of Fish and Wildlife.
Complete Environmental Documentation October  2006  Delay to early 2008 due to difficulty in physically gathering field information and longer review times for Endangered Species Act consultation by US Department of Fish and Wildlife.
Complete Design Documentation May 2007
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $8.0 100%
Right-of-Way $0.0 0%
Construction $0.0 0%
Funded Project Costs $8.0 100%

Nickel funds included in above costs

$6.0 75%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Gary L. McKee, WSDOT Project Engineer @ 206-440-4612 Or E-mail: mckeeg@wsdot.wa.gov

Project Cost Summary reflects the March 2006 Approved Legislative Supplemental Budget