Skip Top Navigation

SR 171 - Moses Lake - Pedestrian Improvements

Countdown to Construction
Starts 2/3/14
Map of SR 171-Broadway Ave in Moses Lake View entire map This project improves or installs new crossings at eight locations in this 3-mile section of Broadway in Moses Lake.

Photo of Crossing Beacon at Dogwood and SR 171 View entire photo  This beacon at Dogwood St. will be replaced with new, more effective lights.

Photo of Crossing Beacons at Driggs and SR 171
View entire photo
This crossing at Driggs Drive will also be upgraded.



Status

Spring 2014

Construction is scheduled to begin April 21, 2014 and should take 30 working days, or about 6 weeks to complete in early June.

This pedestrian safety project upgrades four exisiting pedestrian crossings and installs four new ones along a 3-mile section of Broadway Avenue in Moses Lake.

Why is WSDOT upgrading existing pedestrian crossings and providing new ones along SR 171?
This section of Broadway Avenue in Moses Lake has a history of pedestrian/vehicle collisions. 

In the last five years there have been seven vehicle-pedestrian collisions here. Three of them resulted in fatalities, two produced serious injuries and two more, lesser injuries. WSDOT is partnering with the City of Moses Lake on this grant-funded project to increase safe crossing opportunities for pedestrians on SR 171.

The End Result
The pedestrian crossings at these four locations will have the existing flashing beacons replaced with new rectangular rapid flashing beacons (RRFB). 

  • Driggs Drive at MP 0.35 
  • Burress Avenue at MP 0.82
  • S. Western Avenue at MP 1.65
  • Dogwood Street at MP 2.51

The new, rectangular RRFB lights have  produced 80% to 90% compliance in vehicles yielding to pedestrians at high risk crossings. The existing push buttons will be replaced with audible push buttons to aid the visually impaired.

These four intersections will have new crossings installed with RRFB's, audible push buttons and illumination.

  • Melva Lane at MP 0.20
  • Gibby Road at MP 1.46
  • Gumwood Street at MP 2.32 
  • Third Avenue at MP 3.46

 

Project Benefits
The project provides more and improved opportunities for pedestrians crossing SR 171/Broadway Avenue in Moses Lake.


What is the project timeline?
Construction is scheduled to begin April 21, 2014 and should take 30 working days, or about 6 weeks to complete in early June.

Financial Information

Project signage will reflect the cost of construction engineering, project bid award and sales tax.

A Federal Highway Safety Administration-Quick Response Safety Program grant for $638,244 was awarded for this project on February 12, 2013.

The project was advertised for private contractor bids in August and 2 qualified bids were opened on Sept. 12. On Sept. 24 contract # 8530 was awarded to Colvico, Inc. of Spokane for $401,568.00, 5% under the engineering estimate.

How can I get more information?
Contact:
Josh Patrick, Project Engineer
WSDOT North Central Region
2830 Euclid Ave.
Wenatchee, WA 98801-5916
Phone: (509) 667-2880 or toll free (888) 461-8816
Email: Josh.Patrick@wsdot.wa.gov

back to top