Project Title & Location
SR17/Pioneer Way to Stratford Road - Moses Lake
|
Project Description
This project will expand a three-mile segment of SR 17 from two to four lanes.
|
|
Contractor/Consultant
Project not yet advertised or awarded.
|
|
Recent Progress
This project was initiated in July 1993. Total expenditures as of July 2003 are $1.73m, as shown as the start of the expenditure graph below. Currently the PE and R/W phases are funded and the CN is funded through the 2005 Legislation. The project completed an in-house office review June, 2003 and the Design Documentation Package was approved March 4, 2004. Constructability review with HQ Construction was completed in March 2004.
|
|
Design Construction Impacts
Construction activities will require close coordination with the City of Moses Lake, utility companies, local merchants, schools, and emergency services.
|
|
Environmental Impacts / Compliance
There are two parcels which are potential problems. One is an abandoned gas station, where there is one remaining in-ground oil tank. The other is an abandoned house with the possibility of asbestos contamination. NEPA: Documented CE SEPA: Determination of Non-Significance JARPA application has been submitted
|
Impacts to Traffic
Two-way traffic will be allowed to flow through most of the construction. The interchange ramps will be closed during ramp re-construction for a minimal amount of time. A total of 160 working days are estimated.
|