Recent Progress
Recently completed CEVP considering three scenarios: 1 lane in each direction with minimal interchange improvements, bottleneck projects and HOV lane completion.
$750,000 was advanced in the supplemental budget to begin work on the EIS. EIS is funded in the Nickel Package in 05-07.
WSDOT staff identified potential increase of wetland buffer regulations proposed by DOE, the Army Corp of Engineers and growth management regulations. WSDOT staff has been working with local jurisdictions to update waterland information. We uncovered that King County wetland data is nearly 20 years old.
|