SR 167 - Tacoma to Edgewood New Freeway Construction

Quarterly Project Report Update for Quarter Ending March 2005

Project Title & Location
SR 167 Extension Stage 1 (SR 509 to I-5), Tacoma/Fife
SR 167/I-5 to SR 161 Stage 2, Fife/Puyallup

Project Description
Funds preliminary design engineering and selective right-of-way purchases on a project that will ultimately build a new four-lane freeway from the Port of Tacoma to I-5 and six lanes from I-5 to SR 161 in Puyallup. The latter section includes two general-purpose lanes and one HOV lane in each direction.

Contractor/Consultant
Project not yet advertised or awarded

Recent Progress

Preliminary Design for Stage 1 (SR 509 to I-5) has started. The engineering design team is developing basic roadway alignments and geometry.  Geotechnical investigations have begun in order to provide recommendations for early design decisions. 

A consultant is finishing the Cost Estimate Validation Process (CEVP) Report.  This evaluation of the program will provide updated estimates that will be used to identify funding options for land acquisition and construction.

Carter & Burgess has been hired to help WSDOT determine the best construction sequencing for the project.  On March 29, 2005 the consultant will present their recommendations for construction sequencing for the new freeway from the Port of Tacoma to Interstate 5 (Stage 1).

Design Construction Impacts

Design work is focused on identifying and cataloging issues and risks for further evaluation in the design process.

Environmental Impacts / Compliance
The Tier II Draft environmental impact statement was distributed to the public in February 2003. In response to comments received, additional studies are being performed. The Preliminary Final environmental impact statement is in progress. A Biological Assessment  and Conceptual Mitigation Plan are under development.

Impacts to Traffic
When completed, this project will complete the regional highway plan by providing a freeway connection between the Cities of Puyallup and Tacoma.

Project Milestones Scheduled Attained Milestone Outlook
Start Project Design October 2003 October 2003 Design is moving ahead on those work elements that are not impacted by the Record of Decision for the environmental documentation.
Begin Limited Right-of-Way Acquisition October 2003 October 2003  Purchase of priority parcels continues as funding allows.
Environmental Documentation July 2006   Continuing to work through the Signatory Agency Committee process with hopes of reaching concurrence in the near future.
   

 

Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $33.7  41.4%
Right-of-Way $47.7  58.6%
Construction $  0.0    0.0%
Funded Project Costs $81.4 100.0%

Nickel funds included in above costs

$63.3  77.8%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Steve Fuchs, Project Engineer, (360) 570-6602, fuchss@wsdot.wa.gov