SR 167 - Tacoma to Edgewood New Freeway Construction

Quarterly Project Report Update for Quarter Ending March 2004

Project Title & Location
SR 167 Extension Stage 1 (SR 509 to I-5), Tacoma/Fife
SR 167/I-5 to SR 161 Stage 2, Fife/Puyallup

Project Description
Funds preliminary design engineering and selective right-of-way purchases on a project that will ultimately build a new four-lane freeway from the Port of Tacoma to I-5 and six lanes from I-5 to SR 161 in Puyallup. The latter section includes two general-purpose lanes and one HOV lane in each direction.

Contractor/Consultant
Project not yet advertised or awarded

Recent Progress

Preliminary Design for Stage 1 (SR 509 to I-5) has started.  The engineering design team is developing basic roadway alignments and geometry.  Project work is being coordinated with the City of Fife, Port of Tacoma, City of Tacoma, Pierce County, and the Puyallup Tribe of Indians.

Design Construction Impacts

Work proceeds on identifying and cataloging preliminary design issues for further consideration during the design process.

Environmental Impacts / Compliance
The Tier II Draft EIS was distributed to the public in February 2003.  In response to comments received, additional studies are being performed. The Preliminary Final EIS is in progress. A Wetland Mitigation Site Plan is under development.

Impacts to Traffic
When completed, this project will complete the regional highway plan by providing a freeway connection between the Cities of Puyallup and Tacoma.

Project Milestones Scheduled Attained Milestone Outlook
Start Project Design October 2003 October 2003 Design is moving ahead on those work elements that are not impacted by the Record of Decision for the environmental documentation.
Begin Limited Right-of-Way Acquisition October 2003 October 2003  Purchase of priority parcels continues as funding allows.
Environmental Documentation December 2005   Work is on track to meet this milestone date.
   

 

Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $33.7  41.4%
Right-of-Way $47.7  58.6%
Construction $  0.0    0.0%
Funded Project Costs $81.4 100.0%

Nickel funds included in above costs

$63.3  77.8%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Steve Fuchs, Project Engineer, (360) 570-6602, fuchss@wsdot.wa.gov