Skip Top Navigation

SR 167 - Puyallup River Bridge - Bridge Replacement

Status

Nov. 2014

 
  • See the Olympic Region Weekly Construction and Traffic Update report for current impacts to traffic.
  • Contractor crews have installed deep shafts for new bridge foundations. Crews will construct shafts and caps that will support new bridge girders. This work will occur on weekdays.
  • Steel plate bridge girders are being fabricated. The girders are scheduled to be installed sometime by early 2015. During installation, drivers can expect a series of night lane closures on southbound SR 167.
  • Watch a time-lapse video of the SR 167 Puyallup River bridge move.

This project is using the design-build method of project delivery. WSDOT completed the preliminary design parameters for the new bridge and alignment, project staging, construction, and ultimate configuration.

WSDOT determined this project will be awarded based on a two-step design-build process due to the complex soil conditions. WSDOT provided the design-build team with a baseline structure and construction staging approach, with the opportunity to propose innovations to the baseline plan.

WSDOT obtained the right-of-way and environmental permits necessary to complete the project.

Why is WSDOT replacing the SR 167 Puyallup River Bridge?
The existing steel bridge built in 1925 is structurally deficient and functionally obsolete.

In January of 2011, WSDOT implemented a load restriction requiring vehicles larger than 10,000 pounds gross vehicle weight to use the right lane only. This restriction is due to floor beam deterioration that was detected during a routine bridge inspection. Due to the load restriction and structural deterioration, the bridge replacement project was funded and advanced ahead of the SR 167 – Tacoma to Edgewood New Freeway Construction project.

Crews previously installed steel plates along the underside of the bridge’s steel truss to reinforce the structure so legal-weight trucks can continue to use the 89-year old bridge until the replacement bridge is complete.

The End Result
This project replaces the existing northbound bridge with a new two lane structure while preserving the structural and functional integrity of the roadway.

The new bridge is designed with the capacity to add new lanes in the future if funding becomes available.

Project Benefits

Improved Structure: The new structure will be designed and built to current engineering and seismic standards.

Safety: Wider shoulder, lanes, and an 8-foot sidewalk will enhance bicycle and pedestrian safety.

What is the project timeline?
WSDOT advertised the Request for Qualifications during spring of 2013.

On October 3, 2013, WSDOT awarded a design-build contract to Atkinson Construction for $23.3 million to design and build a replacement northbound bridge over the Puyallup River.

The Design-Build team of Atkinson/Jacobs completed design of the new steel plate girder bridge superstructure to allow steel fabrication to begin during the summer of 2014.

Construction of the new bridge is scheduled to be complete by late 2015.

Financial Information

Financial Data for PIN 316725A
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $31,242
Total $31,242

Project signage will reflect the cost of construction engineering, project bid award and sales tax.

How can I get more information?
Contact:
Brenden Clarke
Project Manager
360-357-2606

Claudia Bingham Baker
Communications Manager
360-357-2789

back to top