SR 167 - 15th Street SW to 15th Street NW - HOV

Quarterly Project Report Update for Quarter Ending September 2004

Project Title & Location
15th St. SW to S. 180th St. Stage 3: HOV Lanes--Auburn to Renton

Project Description
This project reduces congestion by adding a northbound high occupancy vehicle lane and adding ramp meters and high occupancy vehicle bypass lanes at several interchanges.

Contractor/Consultant
Project is not yet advertised or awarded.

Recent Progress

Revised wetland and buffer area impacts have been quantified and mitigation design is complete.  Flood plain impacts were reviewed with design adjustments made to meet local agency requirements.  A Cost Risk Assessment (CRA) was performed to verify project cost estimates. 

Design Construction Impacts

Recent advances in methods to treat and detain storm water runoff made the old design obsolete.  The storm water system has been redesigned to meet the higher-level environmental requirements.  Proposed ramp widening for the SR 18 and 15th SW interchanges is being deleted due to project cost increases, lack of operational benefit and potential incompatibility with future projects.

Environmental Impacts / Compliance
Five-year-old permits obtained for the old design have expired and are in the process of being reapplied for.  SEPA Document is being re-evaluated.

Impacts to Traffic
The project will improve the efficiency of the general purpose and HOV lanes.  Construction will require lane closures at times during non-peak hours.  Public outreach will be conducted.

Project Milestones Scheduled Attained Milestone Outlook
Begin Prelim Engineering (nickel portion) July 2003  July 2003 Project design underway.
Environmental Complete Sept 2005  
Right of Way Certified Sept 05    
Advertisement Oct 2005

 

Open to Traffic July 2008  Project will be complete in two construction seasons by December 2007.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $3.76 8.6%
Right-of-Way $0.0 0.0%
Construction $40.0 91.4%
Funded Project Costs $43.76 100%

Nickel funds included in above costs

$40.36 92.2%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

John E. Johnson, WSDOT Project Engineer (206) 440-4552 or
E-mail:  JohnJoh@wsdot.wa.gov