SR 167 - 15th Street SW to 15th Street NW - HOV - Complete October 2008

Quarterly Project Report Update for Quarter Ending June 2004

Project Title & Location
15th St. SW to S. 180th St. Stage 3: HOV Lanes--Auburn to Renton

Project Description
This project reduces congestion by adding a northbound high occupancy vehicle lane and adding ramp meters and high occupancy vehicle bypass lanes at several interchanges.

Contractor/Consultant
Project is not yet advertised or awarded.

Recent Progress

Revised wetland and buffer area impacts have been quantified and supplied to the landscape office to begin mitigation design for the CORPS permit application anticipated to be submitted in October 04.  Flood plain impacts were reviewed with design adjustments made to meet local agency requirements.  Have been meeting with local agencies to coordinate on their requirements.

Design Construction Impacts

Recent advances in methods to treat and detain storm water runoff made the old design obsolete.  The storm water system is being redesigned to meet the higher-level environmental requirements.

Environmental Impacts / Compliance
Five-year-old permits obtained for the old design have expired.  We must reapply after the storm water system is redesigned.

Impacts to Traffic
The project will improve the efficiency of the general purpose and HOV lanes.  Construction will require lane closures at times during non-peak hours.  Public outreach will be conducted.

Project Milestones Scheduled Attained Milestone Outlook
Begin Prelim Engineering (nickel portion) July 2003  July 2003 Project design underway.
Environmental Complete Feb 2004 Water quality treatment and mitigation revisions have delayed estimated approval to September 2005.
Right of Way Certified NA NA Not Needed
Advertisement Feb 2004

Environmental issues have delayed Ad to Oct 2005.

Open to Traffic Sept 2007 Contract completion is now estimated about July 2008.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $3.76 8.6%
Right-of-Way $0.0 0.0%
Construction $40.0 91.4%
Funded Project Costs $43.76 100%

Nickel funds included in above costs

$40.36 92.2%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

John E. Johnson, WSDOT Project Engineer (206) 440-4552 or