SR 167 - HOT Lanes Pilot Project

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location
SR 167 – HOT Lanes Pilot Project
15th St. SW to I-405
Auburn to Renton

Project Description
This pilot project will convert the existing HOV lanes into High Occupancy and Toll (HOT) lanes; HOV, buses, and motorcycles will still use the lanes toll-free. Single occupant drivers will need a Good To Go!™ transponder to use the HOT lane. The toll rate to enter the HOT lane will change throughout the day depending on the volume of traffic; priority is to maintain a reliable speed within the HOT lane. Tolls will only be collected electronically; there will be no toll booths.

Contractor/Consultant
Perteet Inc. – Gen. Engr’g. Consultant Mgmt. Jacobs Carter Burgess–Tolling Consultant Mgr. ETC – Tolling Vendor Signal Electric – Construction Contractor Bilfinger & Tri-State – I-405 Constr. Contractor

Recent Progress
Tolling Technology - Coordination with Tacoma Narrows Bridge tolling equipment provider. Tolling equipment and Toll Rate sign testing.
Construction - Installing toll rate sign and gantry foundations and electrical work. Coordination with I-405 Renton Design-Build project and HOT Lanes Pilot Project contractors. Striping first of two lane stripes for HOT lane.
Public Outreach - Updated project materials including the HOT Lanes folio, PowerPoint presentation, and web site. Continued public comments tracking and responses. 
Implementation - Finalizing the Performance Monitoring & Evaluation (PME) plan.
Finalizing the Operations, Maintenance & Enforcement (OME) plan.
For more project information see the project web page.

Design Construction Impacts
The northern 1-mile of the HOT Lanes is being constructed by the I-405 Design-Builder (Bilfinger & Tri-State), the remaining 11 miles is being constructed by Signal Electric.

Environmental Impacts / Compliance
An environmental document (DCE) was prepared for, and approved by, the regulatory agencies in late 2006.

Impacts to Traffic
The project will increase capacity and improve traffic operations by converting the HOV lanes to HOT lanes. Construction will require lane closures during non-peak hours.

Project Milestones Scheduled Attained Milestone Outlook
Start Preliminary Engineering Design Spring 2006 April 2007 Design completion.
Start Environmental Documentation Process Spring 2006 Dec 2006 Environmental documents were completed in December 2006.
Start Construction Spring 2007 June 2007 Construction is anticipated to be 1 full construction season.
Open for Tolling Spring 2008
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 3.4 19
Right-of-Way 0 0
Construction 14.5 81
Funded Project Costs 17.9 100.

Nickel funds included in above costs

0 0

2005 Transportation Partnership Account

12.7 71

  For more information, go to www.wsdot.wa.gov/projects

Patty Rubstello , WSDOT Project Manager
(206) 494-1299 or E-mail: rubstep@wsdot.wa.gov