SR 167 - HOT Lanes Pilot Project

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location
SR 167 – HOT Lanes Pilot Project 15th St. SW to I-405 Auburn to Renton

Project Description
This pilot project will convert the existing HOV lanes into High Occupancy and Toll (HOT) lanes; HOV, buses, and motorcycles will still use the lanes toll-free. Single occupant drivers will need a Good To Go!™ transponder to use the HOT lane. The toll rate to enter the HOT lane will change throughout the day depending on the volume of traffic; priority is to maintain a reliable speed within the HOT lane. Tolls will only be collected electronically; there will be no toll booths.

Contractor/Consultant
Perteet Inc. General Engineering consultantCarter Burgess Design/Tolling consultantETC Tolling vendorSignal Electric construction contractor

Recent Progress

· Tolling Technology - Transponder testing.
· Construction -
· Public Outreach - Coordination on outreach responsibilities, messaging, and next steps for public involvement. Updated project materials including the HOT Lanes folio and web site. Continued public comments tracking and responses. 
· Implementation - Began outlines for the Performance Monitoring & Evaluation (PME) plan. Began outlines for the Operations, Maintenance & Enforcement (OME) plan.

For more project information see the project web page at: http://www.wsdot.wa.gov/Projects/SR167/HOTLanes/

Design Construction Impacts
The northern 1-mile of the HOT Lanes is being constructed by the I-405 Design-Builder (Bilfinger & Tri-State), the remaining 11 miles is being constructed by Signal Electric.

Environmental Impacts / Compliance
An environmental document (DCE) was prepared for, and approved by, the regulatory agencies in late 2006.

Impacts to Traffic
The project will increase capacity and improve traffic operations by converting the HOV lanes to HOT lanes. Construction will require lane closures during non-peak hours.

Project Milestones Scheduled Attained Milestone Outlook
Start Preliminary Engineering Spring 2006 April 2007 Design completed
Start Environmental Documentation Process Spring 2006 Dec 2006 Environmental documents were completed in December 2006.
Start Construction Spring 2007 Dec 2006 Construction is anticipated to be 1 full construction season.
Open for Tolling Spring 2008 Tolling will start Spring 2008.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 3.4 19%
Right-of-Way
Construction 14.5 81%
Funded Project Costs 17.9 100%

Nickel funds included in above costs

12.7 71%

2005 Transportation Partnership Account

5.1 29%

  For more information, go to www.wsdot.wa.gov/projects

Patty Rubstello , WSDOT Project Manager @ (425) 450-2720 or E-mail: rubstep@wsdot.wa.gov