Project Title & Location
SR 161 - 36th to Jovita - Additional Lanes
|
Project Description
The purpose of this project is to ease congestion and reduce accidents on SR 161 by adding lane capacity and managing access points. This project will construct one additional lane in each direction, provide sidewalks on both sides, and make intersection improvements.
|
|
Contractor/Consultant
Project not yet advertised or awarded
|
|
Recent Progress
The City of Edgewood, the City of Milton, and WSDOT have agreed that this widening project will construct two lanes in each direction. Additional turn lanes will be provided at intersections. WSDOT is currently considering recommendations from the City of Edgewood contained in Resolution Nos. 05-205 and 06-223. Costs associated with the resolutions were presented to the City of Edgewood in December 2005.
|
|
Design Construction Impacts
Right of way purchase and further design work was halted until the city’s improvement strategy for SR 161 was better understood. Design resumed in summer 2005.
There are numerous utilities in the state right of way throughout the two-mile project corridor. Overhead and underground utilities will have to be relocated prior to Contract Ad. Contract Ad could be delayed if utilities are not relocated by fall 2008.
|
|
Environmental Impacts / Compliance
Storm water will be collected and treated in accordance with current standards.
|
Impacts to Traffic
Public can expect periodic lane closures during construction, and slow-moving traffic through the work area.
|