Skip Top Navigation

SR 160 - Vashon Terminal - Timber Trestle and Terminal Replacement



Vashon Ferry Terminal
View Project Map

typical ferry terminal structure schematic
Typical ferry terminal structures (enlarge)


 

Vashon Ferry Terminal



Trestle timbers at Vashon

Status

February 2015

  • Construction to retrofit the Vashon ferry terminal is scheduled to begin in June 2015.
  • Join us for a community meeting to learn more about what to expect during construction, including modifications to the ferry schedule and operations.
    • Southworth
      Tuesday, March 10 
      5:30 – 7:30 p.m.
      Harper Church
      10384 Southeast Sedgwick Road 
      Port Orchard, WA
    • Vashon
      Thursday, March 12
      5:30 – 8 p.m.
      McMurray Middle School
      9329 Cemetery Road SW 
      Vashon, WA

WSF will upgrade the entire Vashon ferry dock. This framework of timber that serves to support the holding lanes, and pedestrian and vehicle lanes to/from the ramps to the ferry.

Why is WSDOT replacing these structures?
The Vashon ferry terminal provides a critical link between Vashon Island, the Seattle mainland and the communities west of Puget Sound. The existing Vashon ferry dock was constructed in 1957 and is vulnerable to earthquakes.  

The project will bring the entire dock up to current seismic code and allow access to and from the island in the event of an earthquake.

The End Result
This project will retrofit the existing ferry dock by placing seismic braces at 10 critical locations along the dock and replacing about 200 feet of timber trestle with concrete supported by steel piling.

In the event of an earthquake, the main transportation corridor for Vashon Island residents will be better protected. 

Project Benefits

  • Improve Reliability: In the event of an earthquake, both terminals on Vashon Island are at risk. It’s critical that the island’s main terminal be upgraded immediately.
  • Improve Safety: The project brings the dock up to seismic, mechanical and electrical codes.

What is the project timeline?

  • April 2015: Advertise project.
  • June 2015: Begin construction.
  • April 2016: Complete construction.

Financial Information

The total project cost is $15 million. Funding is provided through a mix of federal grants and state funding.

How can I get more information?
Contact:
Frank Fiedler
WSF Design Project Engineer

Joy Goldenberg
WSF Communications Manager
206-515-3411
goldenj@wsdot.wa.gov

back to top